Case Study: Clean fuels

Case study: Clean fuels
Location: Coryton
Client: Foster Wheeler
Project: Clean fuels
End User: BP Oil Ltd
Contract Value: £2.45m
Construction Period: 30 weeks
Year Completed: 2003

Contract Scope:

Approximate quantities of major equipment & materials
Cable containment: 7,700m
Power & instrument cable: 82,000m
Max installed rate for cable: 7,500m/week
Instrument pipework: 6,400m
Instrument loops: 933
Instruments: 1,072
Trace heating cable: 0m
Equipment installation :4 transformers
Switchgear/ MCCs manufacturer: S&I
UPS system: MGE
Fire detection system: Allison
Luminaires: 292 installed
Control system: Foxboro IA

Other information
Safety statistics: RIFR 0, AIFR 3.6
Labour agreement: NAECI Category 1 Coryton contractors agreement
Documentation: Test and inspection sheets

Return to list of case studies