Case Study: Energy from Waste Plant
|
Contract Scope:
Project Details
Boulting Group had two clients on the project and were contracted to manufacture and install MCC panels, Plc Panels and cabling.
- Project Value: £499,366.00
- Contract Duration: 12 months
- Location: Dargavel, Dumfries
Scope of Work
Project Management, Survey, Design, Build, Test, Installation, Commissioning. Boulting Group installed all containment and supports, E&I cabling, fitted instruments and main panels. Glanded, terminated and tested all cables. Boulting panel division manufactured and installed the main MCC panels. Boulting Technology completed the works on the PLC panel.
Services & Equipment Supplied
- Main Panels
- MCC switch room
- Instruments to 2nd thermo-couples
- ID Fans
- Multi Blocks
- HV substation
- Burner limit switches
- 8 x burners
- Cooling water
- Turbine generator
- Flue Gas Recirculation fans
- Emergency standby generator
- Bore hole lean to
- Conveyor
- Fire pump station
- Cable testing and inspection
- Fibre optic cabling
- IT cabling
Cable sizes range from:
4c x 400mm Mains, 4c x 120mmm sub mains to Multicore cable 19c to 7c, instrument cable 2pr screened and overall screened. The full range of cable sizes were utilised as per the cable schedules. Installation of some specialist high temperature cable.
Total cable length installed
Client 1 = Approximately 31,000 metres
Client 2 = Approximately 9,000 metres