Case Study: Local Sludge Treatment Plant
Contract Scope:
The water will be stored in 3 storage vessels to be transferred at a later date into an encapsulation plant. The welding build quality was the highest criteria set out by the client and the first project of this standard for a number of years. Boulting installed all the interconnecting pipework and all the electrical services as detailed.
The following details highlight the size and scope of this project:
- Project Value: 4.2 million
- Total Man-hours: 52550
- Contract Duration: 18 months
- Peak Manning Level: 45 men
Services and equipment
Electrical Scope
- New Modularised Switchroom 1
- Trunking/Tray Containment 1500 meters
- Instrument/Power JB's 45
- Power Cable 2500 meters
- Instrument Cable 10500 meters
- Instruments 150
- Instrument Pipework 250 meters
- General Lighting 120
- Emergency Lighting 45
- 240v/110v Small Power Sockets 55
- Fire Alarm 70 points
- Trace Heating 155 meters
- Earth Ring Main System 1
- Lightening Protection System 1
- Communication Voice/Data 10
Mechanical Scope
- Isometrics 340
- Stainless Steel Pipework 2400 meters
- Carbon Steel Pipework 600 meters
- Secondary Steel Supports 265
- Build 1 Welds Site 459 Off site 163
- Build 2 Welds Site 278 Off site 2
- Build 5 Welds Site 255 Off site 63
- Build 6 Welds Site 160 Off site 23
Other Information
- Safety Statistics: RIFR 0, AIFR 0
- Labour Agreement: NAECI Categorised
Boulting Group Subcontractors Controlled Activities:
- Lightning Protection, Fire Alarm Commissioning
- NDT(X-Ray & Gamma) & Painting.