Case Study: Replacement GMP receivers

Case study: Replacement GMP receivers
Client: AstraZeneca
Project: Replacement GMP receivers

Contract Scope:

The Boulting Group was asked to replace two existing horizontal, non-agitated receivers with new vertical, glass-lined, agitated receivers as part of a GMP improvement project.

New instrumentation was required to measure vessel contents’ temperature, via the baffle and the bottom run-off valve, and load cells were needed to measure content. A sampling system was provided for the vessel contents.

Operator access platforms were implemented, to allow operator/maintenance access to the vessel-head for inspection and sample-taking. A lifting beam was installed to allow top works removal.

Services supplied

  • Scope development, including HAZOP
  • Detailed design and engineering and relief stream verification
  • CDM role as principal contractor
  • Installation
  • Validation activities, including preparation of IQ and OQ and execution
  • Calibration
  • Hazardous area inspections
  • Commissioning

Equipment supplied

 

  • Structural steelwork, platforms, lifting beam and hoist
  • Pipework including lined pipe
  • Sample system
  • Inline items including bursting discs, filters, sight glasses, valves
  • Load cells, temperature transmitters and local indicators
  • VSD cabinets