Case Study: WwTW - new MCC and SCADA system

Case study: WwTW - new MCC and SCADA system
Client: Major water supplier
Project: WwTW - new MCC and SCADA system

Contract Scope:

The project required new aeration lanes, settlement and sludge tanks, pumping stations and CSO modifications.

A new MCC with PLC was provided, interfacing to the existing PLCs over a DH+ network. A new de-waterer PLC and HMI was also provided on this network.

A new SCADA system was provided for both the new and existing plant, with UPS backup. Visualisation was with a Rockwell RSView 32 client/server SCADA solution, with one client. The interface to the telemetry system was via a modbus link.

Services supplied

  • CAPEX input
  • MCC GA and schematic drawings
  • G5/4 compliance harmonic survey
  • FDS development
  • System build
  • PLC software configuration
  • SCADA graphics
  • FAT, SAT and commissioning
  • Delivery and installation

Equipment supplied

  • Form 4 type 3 MCC, 10m length
  • Back to back, IP54, 50kA for 1s
  • 2x90kW and 3x18kW VSDs, 15 DOLs, 2 ASDs
  • Sub MCCs for another site
  • Rockwell ControlLogix PLCs, PanelView HMI and DH+, Modbus, ControlNet equipment
  • SCADA PC and SCADA client PC

 