Since August 2011 Boulting has been conducting a series of Arc Flash Incident Energy studies across five Combined Cycle Gas Turbine (CCGT) power stations.

The U.S based Client operates several CCGT power stations across Europe, producing a total of 3,700 Megawatts of power to the National Grid. It built it's first CCGT site in the U.K. back in 1998 and since then the U.S. have introduced new legislation and standards for the protection of workers in the Electrical Industry from the effects of Arc Flash Incidents from electrical equipment.

At present there are only U.S. standards for Arch Flash protection in existence (in this case IEEE 1584 & NFPA 70E). As it is not yet law in the U.K. or Europe very few companies in the U.K. carry out this type of specialist study work.

However, as a responsible company, the Client required its European sites to be brought in line with U.S. legislation - even though it is not required by European law.

In March 2011 Boulting were invited to give a presentation to the Client's Senior Electrical Engineers, alongside three other consultancies who also had experience in Arc Flash Studies. The Boulting presentation came out on top and was praised for demonstrating a broad knowledge and experience of the subject matter.

Boulting were awarded the £132K, four month contract and work commenced in August 2011.

Scope of works included:

  • Site surveys were conducted on all five sites. The findings were used to produce follow-on production of Short Circuit Fault calculations and system analysis reports.
  • Arc Flash Energy Studies were then carried out and recommendations made for Arc Flash mitigation measures where the calculated Incident Energy levels were higher than U.S. industry accepted standards.

The study is now nearing completion and the Client has praised the Boulting Team for completing the studies within their very tight timescales.

For more information on Arc Flash Protection read our case study: Arc Flash: Know the Risks.

Highlights


Collaboration from concept to construction
Read our take on the benefits of integrated project delivery (IPD) and the collaborative culture it produces.

Read more

Engineering standards and the importance of professional registration
Here, Glyn Shawcross, Boulting Design Manager, explores the importance of working with accredited contractors who invest in training for employees.

Read more